Construction Overview for June 5, 2020
June 5, 2020
Construction Overview for June 05, 2020
We are excited to share with the community the progress on site. The forming contractor has poured a large section of the Slab on Grade and has commenced installation of the forming for the suspended slab at Parking Level 4, as we continue to diligently employ our COVID-19 safety procedures.
If you have any questions please contact us at: construction.social@pemberton.com.
We thank you for your patience and cooperation.