Recent construction activities have focused on the bulk excavation & wood lagging installation along the North side of the site. The installation of the truck the staging platform also continued along the North side of the project and is now mostly complete.
This week, the excavation & wood lagging activities will continue along the North and East areas of the project with material being removed on a daily basis. The truck staging platform requires a few more days next week to be fully completed. Beginning stages of the concrete work will commence towards the end of the week on the project.