Construction Update: August 20, 2021
August 20, 2021
The Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
During the week of August 16, 2021, continued to focus on formwork on the South half, and rebar/ concrete placement on the North half of the Ground floor. The Team completed the pouring of another section of the Ground floor slab on the North West side, the pouring of all the vertical concrete structure to Ground floor and poured the first columns to Level 2. The formwork and rebar installations for the vertical concrete structure to Level 2 in the NW corner of the site continues to progress.
For the upcoming week of August 23, 2021, the Site Teams will continue to pouring another section of the Ground floor slab and continue with the formwork on the South West half of the Ground Floor. We also will continue pouring the vertical concrete structure to Level 2 at the North West corner of the site.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity, please contact us at: 543richmond@pembertongroup.com
For regular updates, please visit our webpage by clicking on this link, Construction Update Link: https://pembertongroup.com/543-richmond/construction-update/
We thank you for your continued patience and cooperation.