Construction Overview Dec-24 to Dec-31-2022
December 23, 2022
Construction Overview for Dec 24, 2022
There will be NO construction activities taking place on Saturday, Dec 24, 2022 in lieu of the holiday season.
Construction Overview for Dec 26 – Dec 30, 2022
Our Site will closed on Dec-26 and Dec-27 due to the public holidays. During Dec-28 and Dec-30, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
North end concrete construction activities will continue. Construction crews will be completing walls from MPH to Roof and the floating slab on the MPH Floor. We are preparing for the various amenities on the 11th Floor and are waterproofing the floor. Interior suite finishes have also started on 3rd and up floors of both north buildings. Northwest hoist has been extended up to 30th floor and we are preparing to install a hoist on the northeast side that will also go up to 30th Floor.
North side glazing crews are continuing with the installation of metal panels and windows from 15th to 19th floors. Balcony posts have also begun on the north side. The link windows between the North and South buildings are being installed from 15th and up. Fan coils, standpipes and duct work in the north will continue to commence. Curtain wall is also under construction on the ground floor on the west and north side.
Civil works are being done around the perimeter of the buildings and we are installing the manholes and the associated pipe work. We are also chipping caisson walls and backfilling with recommended soil as a part of landscape work around the east and south of the project.
On the South side, interior construction development and finishing is continuing to progress. We are also triggering lobbies and townhouses on the Ground and Level 1, as we approach to close the south buildings. Window wall is complete on both south towers. The windows in the hoist suites of building D have almost been done as the hoist is down now. We are installing windows in the hoist on Building C to close the building. Railing work will continue on both south towers.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com