Construction Overview – March 20, 2020
March 20, 2020
We have had a very successful week and would like to thank our neighbours and the local community for assisting us in our efforts.
At the end of this week, the project reached another key milestone. The demolition of the existing basement floor and the remaining portion of the foundation wall on the east perimeter was completed. By reaching this milestone, the concrete hammering operation has come to an end which is a relief to both the project and our neighbours.
The backfilling program continued throughout the week with the majority of the site covered with the first layers of backfill material.
Concrete patching repairs to the foundation wall of 555 Richmond were also completed this week.
For the week of March 23, 2020, we will be focusing on the backfilling of the old building footprint. There will be a high volume of trucks coming to the site over the next 2 weeks in order to complete this task.
Also, waterproofing and plating of the foundation wall at 555 Richmond will be completed by the end of the week.
If you have questions regarding construction activity please contact us at: 543richmond@pembertongroup.com or call 647.351.4120.
We thank you for your patience and cooperation.