Construction Overview for April 11 – April 15, 2022
April 11, 2022
During the week of April 11, 2022, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
North Towers:
North end construction continues to progress, crews will be completing level 12 and continuing with level 13 slab pours. Level 13-14 verticals will be getting formed and poured.
South Towers:
On the South side, construction is steadily progressing and the balcony railings continue to arrive on site and are in the installation phase. Glazing work continues on the exterior of the south towers, as well as, the installation of metal panels. Crews continue boarding the South West Tower.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic. If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com