Construction Overview for April 18, 2020
April 17, 2020
There will be work Saturday, April 18, 2020, on-site from 9:00 am until approximately 3:00 pm at 177 Front Street East.
The crews will be continuing to form for concrete and rebar installation in the north and west sides.