Construction Overview for August 31, 2020
August 31, 2020
The construction team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
Work continues on the forming, framing and pouring for the second floor on the north side.
Crews will continue building suspended decking as part of the preparation for the Ground Floor concrete pours on the southeast side. The remaining Ground Floor slab on the south side will be poured.
Concrete trucks will enter and depart the site from Princess street, Lower Sherbourne and The Esplanade.
During gate operations, flag people will control the gates to ensure the safety of pedestrians and to minimize any impact on traffic.