Construction Overview for August 31, 2020



August 31, 2020

Construction Overview for August 31, 2020

The Below Grade Shoring activities progressed well over the past week and continue to be the main focus on site. This week drilling commenced on the East side of the project and will continue for the next few weeks.

The Shoring work on the South side of the project is now complete, increasing the production of the excavation work. The Dewatering System is fully commissioned and is now active.

The Below Grade Shoring and Excavation work will continue to be the main activities on site next week. There will be a steady flow of trucks throughout the week.

If you have questions regarding construction activity please contact us at: 543richmond@pembertongroup.com.