Construction Overview for Dec 02 – 06, 2019
November 29, 2019
This week and over the course of the next few weeks, the focus of work on the site will be forming/pouring the structural slab, columns and garage roof in the north and west sides.
Also, work is steadily progressing on the external site servicing installation and waterproofing.
Concrete trucks will enter and depart the site from Princess street.
During gate operations, flag people will control the gates to ensure the safety of pedestrians and to minimize any impact on traffic.