Construction Overview for Jan 24 – 28, 2021
January 24, 2022
During the week of January 24, 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
North Side:
Construction Crews continue forming and pouring on Level 11, as well as, the construction of Level 11- 12 verticals.
South Side:
On the South East Tower, construction crews will be constructing the forming of verticals to roof and lifting mechanical penthouse equipment. The South West curtain wall glass panels are currently being installed and waterproofing and interior studs installation continues throughout the South Towers.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com