Construction Overview for July 29 – August 02, 2019
July 26, 2019
This week will see the continuation of excavation and soil removal in the southern of the property. Work is also steadily progressing on the chipping caissons, pouring of the mud slab and waterproofing in the north side.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com