Construction Overview for July 30, 2020
July 30, 2020
Construction Overview for July 30, 2020
The below grade excavation and shoring activities continue to be the main focus and ramped up to full production over the past week. The dewatering piping system also progressed well and will be completed by the end of the month.
The below grade activities will continue next week and will be ongoing into September. We will also be reaching another key milestone next week, as the temporary power substation will be energized which will allow us to commission and run the dewatering system.
If you have questions regarding construction activity, please contact us at: 543richmond@pemberton.com.
We thank you for your patience and cooperation.