Address

50 Confederation Parkway
Concord, ON
L4K 4T8

Hours

Open

Monday-Friday: from 8 am - 5 pm

Contact Information

5556

Floorplans

Features

Area Amenities

Site Plan

Contact

Renderings

Construction Update

Back to Property

Construction Update

Register

Construction Overview for June 5, 2020



June 5, 2020

Shoring and site enabling activities progressed well this week. The majority of the vertical shoring work along the south side of the project is complete. The temporary power substation installation is also nearing completion.

Next week, the site will be ramping up activities. Shoring enabling work along Richmond Street will begin on Monday and continue through the week. This will allow the vertical drilling to start later in the week as a second drill will be mobilized to site. The drilling will also continue along the east and west sides of the project. The dewatering contractor will be mobilizing to site next week and will be starting to drill the wells along the south portion of the project.

Please be advised that we will be closing the south parking lane along Richmond Street throughout the week between 7am – 4 pm to facilitate the shoring enabling work along the north side of the project.

If you have questions regarding construction activity please contact us at: 543richmond@pembertongroup.com.

We thank you for your patience and cooperation.