Construction Overview for June 10 – 14, 2019
June 7, 2019
This week will see the continuation of excavation and soil removal. During excavation, trucks will enter and depart from Lower Sherbourne Street.
Pouring the concrete for the mud slab will start in the northern side of the property.
Overhead protection is complete and lighting will be installed inside the overhead protection to illuminate the sidewalks. Also hoarding painting will be started.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com