Construction Overview for June 28th- July 2nd , 2021
August 9, 2021
During the week of June 28, 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
As construction continues on the North side, work this coming week will focus on pouring the 5th floor slab, along with the initial columns and walls rising from the 5th floor to the 6th floor.
Construction work progressively continues on the South side. On the SE side, construction crews will be implementing pour for level 12 slabs and level 12-13 verticals. Construction work will also include pouring Level 14 slab and level 14-15 verticals on the SW side.
In other construction progress, window installation will continue on the south side.
Work is progressing on-site to set up the hoist (external construction elevator) on the South East Side.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com