Construction Overview for March 14 – March 18, 2022
March 11, 2022
During the week of March 14, 2022, crews will continue to pour Level 5 Slab on the North-West and will complete the pouring of the last two sections of Level 4 Slab on the South-East quadrant of the project. Pouring of the vertical concrete structures to Level 4 will be completed and the continuation with the verticals to Level 5-6 throughout the project. Level 4 slab framing will be complete on the South half of the project and Level 5 will continue on the North half portion of the site.