Construction Overview for March 7 – March 11, 2022
March 11, 2022
This week Constructions Crews continued pouring Level 4 Slab on the South-West, as well as, poured the first section on L5 Slab on the North-West of the project. Also, continued pouring the vertical concrete structure to Level 4 on the South half; the verticals to Level 5 on the North half and started the Verticals to L6 on the North-West of the project. Progress continues with the framing of Level 4 slab on the South side and of Level 5 slab on the North side of the project. Mechanical and Electrical installations also continued throughout the garage and the Ground Floor. Grinding of walls and columns continued on P2 and started on P1.