Construction Overview and Look Ahead for the Week of May 11, 2020
May 8, 2020
There will be no work, this Saturday, May 9, 2020.
The construction team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
The remaining Ground Floor slab on the north side will be poured. Crews will continue building suspended decking as part of the preparation for the Ground Floor concrete pours on the west and northwest sides.
Also, work is steadily progressing on the waterproofing, installing under-slab drains on the southeast side.
Concrete trucks will enter and depart the site from Princess street and Lower Sherbourne.
During gate operations, flag people will control the gates to ensure the safety of pedestrians and to minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com.