Construction Overview for May 15, 2020
May 15, 2020
The project ramped up activities over the past week. The shoring equipment was mobilized and has been prepared to start the drilling. The site completed the relocation of some existing services and also installed some temporary services for the project.
Next week the shoring installation will begin and the site preparation activities will continue.
If you have questions regarding construction activity please contact us at: 543richmond@pembertongroup.com.
We thank you for your patience and cooperation.