Construction Overview for Nov 11 – Nov 15, 2019
November 11, 2019
This week will see the continuation of bulk excavation in the middle of the property, waterproofing, granular base and drain installation and forming/pouring the structural slab and columns.
Work is also steadily progressing on the external site servicing installation.
Concrete trucks will enter and depart the site from Princess street.
During gate operations, flag people will control the gates to ensure the safety of pedestrians and to minimize any impact on traffic.