Construction Overview for Nov 15th – Nov 19th, 2021
November 12, 2021
During the week of November 15th, 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
On the North side underground parking level, cupolex concrete pour has been completed. Also on the North end , Level 10 concrete slabs will also be completed. North side crews will be implementing Level 11 slab and forming and pouring Level 10- 11 verticals.
On the South East Tower, construction crews will be finishing Level 18 slab and starting Level 19 Slab, as well as, the forming of 19-20 vertical’s
Also on the South, construction crews will be pouring the South West roof.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com