Construction Overview for Nov 1st – Nov 5th, 2021
October 29, 2021
During the week of November 1st 2021 , the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
We continue to pour at the North side parking level and are approximately 90 % complete. Pouring on the North side includes Level 9-10 slab pour and Level 10 -11 verticals.
On the South East Tower, construction crews will be forming and pouring Level 17 Slab. Level 19 on the SW side is still in production; construction crews are continuing the wall pours for Level 19.
Glazing work still continues on the exterior of the south towers, as well as, the installation of metal panels. We are planning to extend the West Side Hoist in the upcoming weeks.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com