Construction Overview for Nov 29th – Dec 3rd, 2021
November 26, 2021
During the week of November 29th, 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the
Ministry of Labour’s recommendations.
On the North end, Level 10 concrete slabs are completed and Construction Crews are forming and pouring Level 10-11 verticals. North side crews will be implementing Level 11 slabs to follow after the verticals.
On the South East Tower, Construction Crews are pouring Level 19 slab, as well as, the forming of 19-20 vertical’s.
On the South West Tower, Construction Crews will be completing the Tower and pouring any remaining curbs and crane openings. The South West Hoist has been extended to level 19 and the South East Hoist will be extended in the upcoming weeks.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com