Construction Overview for Nov 8th – Nov 12th, 2021
November 5, 2021
During the week of November 8th 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
On the North side underground parking level, cupolex concrete pour is still ongoing and should be completed during the week of Nov 8th. Also on the North end , Level 10 concrete slabs will be in line to get poured. North Side Crews will be forming Level 10- 11 verticals as well.
On the South East Tower, Construction Crews will be pouring Level 17 Slab and forming Level 17- 18 verticals. Also on the South, Construction Crews will be starting the forming and layout of the South West Roof.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com