Construction Overview for November 14-25, 2022
November 18, 2022
Construction Overview for November 14-18, 2022
During November 14-18, 2022, the project progressed well with formwork, rebar and concrete placement on Level 15 and the Roof. This week, the Construction Team was able to pour and complete the last sections of Level 15 Slab on the South-East. Pouring continued along the vertical concrete structures to Roof throughout the project. The Construction Team continued the fly forms and framing of the Lower Roof slab on the South half.
Mechanical and Electrical installations continued throughout GF-L9. Precast erection continued wrapping around Level 6 and Level 7. Window wall installation continued on Level 2 and started on Level 3.
Construction Overview for November 21-25, 2022
During November 21-25, 2022, the Construction Team will focus on pouring the first two sections of Lower Roof on the North-West and continue pouring the vertical concrete structures to Roof throughout the project. The Lower Roof fly forms and framing will be completed on the South half.
If you have questions regarding construction activity, please contact us at: 543richmond@pembertongroup.com
For regular updates, please visit our webpage by clicking on this link, Construction Update Link: https://pembertongroup.com/543-richmond/construction-update/