Construction Overview for November 28 – December 09, 2022
December 5, 2022
Construction Overview for November 28-December 2, 2022
During the week of November 28-December 2, 2022, the project progressed well with formwork, rebar and concrete placement on the Roof Slab. This week, the Construction Team was able to pour three additional sections of Lower Roof Slab on the North-West and complete the pouring of the vertical concrete structures to Roof throughout the project. Additionally, the Team continued the fly forms and framing of the Lower Roof slab on the South-West. Mechanical and Electrical installations continued throughout GF-L9. Precast erection continued wrapping around Level 7 and Level 8. Window wall installation continued on Level 2 and Level 3.
Construction Overview for December 5-9, 2022
During December 5-9, 2022, site crews are scheduled to pour and complete the last two sections of Lower Roof on the South-West. Crews will be prepared to pour the up-turn vertical concrete structures to Upper Roof. Lower Roof fly forms and framing will be completed on the South-West.
If you have questions regarding construction activity, please contact us at: 543richmond@pembertongroup.com
For regular updates, please visit our webpage by clicking on this link, Construction Update Link: https://pembertongroup.com/543-richmond/construction-update/