Construction Overview for Oct 11th – Oct 15th, 2021
October 12, 2021
During the week of October 11th 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
In the parking level, the South portion of the cupolex has been poured and completed; the North side cupolex installation is ongoing and progressing well. .
On the North end, Level 9 concrete slabs are still getting formed and poured and should be completed in the next coming weeks.
On the South East tower, construction crews will be pouring Level 16 slab and 16-17 verticals. Level 19 slab on the South West Tower will still be in progress and is expected to be poured as well.
Corridor studs for the South Towers are still in production and suite studs will be commencing in the upcoming weeks. Glazing work still continues on the exterior of the South Towers, as well as, the installation of metal panels.
Masonry work is ongoing for both Towers. South East side hoist has been extended and we will be implementing the extension of the South West hoist in the upcoming weeks.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com