Construction Overview for Oct 18th – Oct 22nd, 2021
October 21, 2021
During the week of October 18th 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
In the North side parking level, cupolex concrete pour will be ongoing and targeting completion for the week of October 25, 2021. On the North end , level 8 will be finished, Level 9 concrete slabs are still getting formed and poured. Level 10 slabs will be starting to get formed and poured on the North side as well.
On the South East Tower, construction crews will be pouring and finishing up Level 16 slab and 16-17 Verticals; forming and pouring will commence on the Level 17 slab. Level 19 slab on the South West is in production. Construction for Level 19 Roof verticals is expected to be completed the following week.
Corridor studs for the South towers are still in production and suite studs have been started. Glazing work still continues on the exterior of the South Towers, as well as, the installation of metal panels.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com