Construction Update

Register

Construction Overview for Oct 24 – Oct 28, 2022



October 21, 2022

During the week of Oct 24, 2022, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.

North end concrete construction activities will continue. Construction crews will be completing level 29 and 30 slab pours and verticals. The swimming pool on 11th Amenity Floor is also under construction and we are laying mechanical pipes and top rebar layer.

North side glazing crews are continuing with the installation of metal panels and windows on 12th and 14th floors. We have started installing windows on the link between the North and South buildings and are finished up to 8th Floor. Fan coils, standpipes and duct work in the north will continue to commence. Curtain walls and metal canopy is also under construction on the ground floor on the northwest side. Ramp access to northeast side of the building has been waterproofed and we are preparing to pour concrete topping on top of it.

On the South side, interior construction development is continuing to progress. Suite rough ins and finishes are taking place on both south towers. As the cold weather approaches, we are water proofing and placing ballast on MPH Roof on both south towers and we have also done the green roofs. We are also preparing to work on the landscape of the privately owned publicly accessible courtyard. We are triggering lobbies and townhouses on the Ground and Level 1, as we approach to close the south buildings.

Window wall is complete on both south towers. We are preparing to install the windows in the hoist suites of the building D after which we will take down the hoist on building D. Planter walls have been poured outside townhouses as a part of landscape work and we are waterproofing the planters as well. Railing work will continue on both south towers. Balconies are being coated for weather protection.

During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.

If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com