Construction Overview for October 7, 2022
October 7, 2022
The 543 Richmond Street West project is progressing well with formwork, rebar and concrete placement on Level 14 and Level 15. This week pouring occurred for the Level 14 Slab on the North-East and on the South-East. Concrete pouring to the vertical structures continues on Level 15 throughout the project. Mechanical and Electrical installations continued throughout GF-L7.
Precast erection continued wrapping around Level 2 and Level 3.
For the week of October 10, 2022, the site crews are scheduled to pour and complete the last three sections of Level 14 Slab on the South side of the site. Crews will continue pouring the vertical concrete structures to Level 15 throughout the project. Window installation mobilization to begin on Level 2.
If you have questions regarding construction activity, please contact us at: 543richmond@pembertongroup.com
For regular updates, please visit our webpage by clicking on this link, Construction Update Link: https://pembertongroup.com/543-richmond/construction-update/