Construction Overview for September 27th – October 1st, 2021
September 24, 2021
During the week of September 27th, 2021, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
In the parking level , Cupolex installation is progressing well and should be completed in the next few weeks. On the North end, Level 9 concrete slab will be getting poured as well as the forming of 9-10 verticals.
On the Southeast tower, construction crews will still be getting ready to pour Level 15 slab and 15-16 verticals. Level 19 on the Southwest tower is still in progress, the forming still needs to be complete for the mechanical penthouse.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com