Construction Overview for September 28, 2020
September 28, 2020
Construction Overview for September 28, 2020
The project had another productive week with another milestone achieved as the internal below grade bracing installations were completed. The excavation of the site to subgrade level continued throughout the week and progressed well and will continue to be the main activity on site. The installation of the truck platform along the North side of the project at the future staging area for the project continued and is on schedule to be completed in a couple of weeks.
Next week, the excavation activities will continue at the beginning of the week. We will be installing some external bracing mid week which will restrict the trucking access to the site, but this bracing work is the last installation of the overall bracing design and will be another key milestone achievement.
If you have questions regarding construction activity please contact us at: 543richmond@pembertongroup.com.
We thank you for your patience and cooperation.