Construction Overview for Week of October 17, 2022
October 21, 2022
For the week of October 17, 2022, the project site crews continued to progress with formwork, rebar and concrete placement on Level 15 and poured the first section of Level 15 Slab on the North-West. Also, crews completed pouring the vertical concrete structures to Level 15 and started the verticals to Roof. Mechanical and Electrical installations continued throughout GF-L7. Precast erection continued wrapping around Level 3 and Level 4.
Window wall installation prepping started for Level 2
Looking ahead, crews are scheduled to pour another section of Level 15 Slab on the North-West and continue pouring the vertical concrete structures to Roof throughout the project. On Level 15, fly forms and framing will be completed on the South half and the Lower Roof and framing will commence on the North-West side.
If you have questions regarding construction activity, please contact us at: 543richmond@pembertongroup.com
For regular updates, please visit our webpage by clicking on this link, Construction Update Link: https://pembertongroup.com/543-richmond/construction-update/