Construction Overview Mar-04 to Mar-10-2023
March 3, 2023
There will be construction activities taking place on Saturday, Mar 04, 2023.
Construction Overview for Mar 06 – Mar 10, 2023
During Mar 06 and Mar-10, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.
North end concrete construction activities have been almost finished, with some roof curbs to be poured only. Glazing crews are continuing with the installation of metal panels and windows and finishing some metal panels as well. Balcony posts and railings will continue on the north side. Fan coils, standpipes and duct work in the north will continue to commence. Curtain wall is also under construction on the ground floor on the east, west and north side.
Landscaping work has commenced in the south buildings. Epoxy of South Parking level is also on its way. Window wall is complete on both south towers, and we are finishing up railing work on balconies. The windows on hoist of Bldg C are complete as we approach to remove this hoist starting next week.
During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.
If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com