Address

50 Confederation Parkway
Concord, ON
L4K 4T8

Hours

Open

Monday-Friday: from 8 am - 5 pm

Contact Information

50765

Features

Area Amenities

Site Plan

Contact

Renderings

Construction Update

Virtual Tour Video

Back to Property

Construction Update

Register

Construction Overview Nov-12 to Nov-18-2022



November 11, 2022

Construction Overview for Nov 12, 2022

There will be construction activities taking place on Saturday, Nov 12, 2022.

Construction Overview for Nov 14 – Nov 18, 2022

During Nov-14 and Nov-18, the Construction Team will continue with regular construction activities on the site while following the guidelines set out by Ontario’s Health officials and the Ministry of Labour’s recommendations.

North end concrete construction activities will continue. Construction crews will be completing level 30 and MPH slab pours and verticals. The swimming pool on 11th Amenity Floor is also under construction and we have poured concrete on it and are preparing for rough ins for the walls. Interior suite finishes have also started on 3rd and 5th floor of both north buildings. We are also waterproofing outdoor amenities on 18th floor.

North side glazing crews are continuing with the installation of metal panels and windows on 14th, 15th and 16th floors. We have started installing windows on the link between the North and South buildings and are finished up to 9th Floor. Fan coils, standpipes and duct work in the north will continue to commence. Curtain wall is also under construction on the ground floor on the northwest side.

On the South side, interior construction development is continuing to progress. Suite rough ins and finishes are taking place on both south towers. As the cold weather approaches, we have done water proofing and placing ballast on MPH Roof on both south towers and we have also done the green roofs. We are preparing to work on the landscape of the privately owned publicly accessible areas. We are also triggering lobbies and townhouses on the Ground and Level 1, as we approach to close the south buildings.

Window wall is complete on both south towers. The windows in the hoist suites of building D have almost been done as we are taking down the hoist this week. Planter walls have been poured outside townhouses as a part of landscape work and we are preparing for the entrance stairs. Railing work will continue on both south towers.

During gate operations, flag people will control the gates to ensure pedestrians’ safety and minimize any impact on traffic.

If you have questions regarding construction activity please contact us at: construction.timeandspace@pembertongroup.com