Construction Progress Update – October 23, 2020
October 23, 2020
This week the project was impacted by poor weather conditions again, which caused delays to the progress on site. The main activities this week were the excavation & wood lagging installations along the North & East sides of the site, winter protection of the shoring walls on the West & South sides of the project, and the completion of the truck platform along the North side of the project.
Next week, the excavation & wood lagging activities will continue along the North and East areas of the project. The winter protection of the shoring walls will continue on the South side and will begin on the North side later in the week. Weather permitting, the first stages of the concrete work on the project will begin by the end of the week.