Construction Update: November 9, 2020
November 20, 2020
During the week of November 2, 2020, the project was very productive with a few more milestones being achieved. The majority of the bulk excavation & wood lagging was completed with only the access ramp area left to finish over the next few weeks. The winter protection of the shoring walls is also nearing completion. The waterproofing and concrete topping in the SW quadrant of the project was completed.
For this week, the project will begin to transition towards the concrete portion of the schedule. The West crane base is scheduled to be poured next week in preparation for erecting this crane in the next few weeks. There will be some minor excavation and winter protection work continuing as well.
If you have questions regarding construction activity, please contact us at: 543richmond@pembertongroup.com
We thank you for your patience and cooperation.